The school building is located in a dynamic district, complements a nearby institute building and provides a comprehensive teaching environment with relatively modest means.
LEARNING IN A COMMERCIAL AND RESIDENTIAL ZONE
The Lycée Français, a private school run by parents, has been based in the greater Zurich area since 1956. It educates children and adolescents from kindergarten age up to the Swiss university entrance qualification (baccalauréat). For a long time, the school was accommodated across various properties in the Zurich suburb of Dübendorf. Since 2016, it has occupied its own new building in Neugut, right near Zurich’s north-eastern city limit. This young, dynamically developing part of Dübendorf is one of the eleven priority centres earmarked for dense urban development in the Zurich cantonal structure plan. Several high-rise buildings extend into the sky in the immediate vicinity. In more ways than one, it is fitting that the new school was built on Zukunftsstrasse (literally: 'Future Street').
Around five years later, it became clear that the Lycée Français needed additional instructional space for approximately 600 new pupils. An undeveloped plot was found roughly 100 metres away from the new school building, directly across the same neighbourhood street. Here, the street is called Lagerstrasse (literally: 'Warehouse Street'), pointing to an industrial and commercial past that is still in evidence today. The extension was designed by the same architecture firm responsible for the original building. During planning, the firm had to navigate a heterogeneous setting composed of office blocks, commercial facilities, low-rise residential housing and commercial nursery greenhouses. The school named the extension the 'Bâtiment Auguste Piccard'. The building name commemorates the Swiss world-record balloon pioneer who ascended into the stratosphere from Dübendorf in 1932.
COMPACT, COMPLETE SCHOOL UNIT
The four-storey building with a basement accommodates all instructional functions. It operates as an independent full-day school complete with sports halls, an on-site commercial kitchen and a canteen. The structure was fitted neatly into the rectangular site like a puzzle piece. The remaining narrow strip of open green space is laid out as a footpath encircling the building, while trees on adjacent properties provide shade. Facing the street, the top two storeys cantilever outwards to create a covered entrance area that also accommodates bicycle parking. The roof terrace features a generous break area, a multipurpose playing field and a rooftop garden. The rear-ventilated façade pairs flat metal panels with blue and grey trapezoidal sheet panels, blending the building comfortably into the neighbouring utilitarian structures.
The vertical ribbing of the corrugated panels accents the spandrel zones, while the stairwells, detailed with round window openings, run uninterrupted across all floors. These design strategies lend the structure a lightness that balances the density achieved. The circular theme reappears inside on the vision panels of the classroom doors, while a vibrant colour scheme delineates separate functional zones. Exposed overhead service lines and ventilation ducts serve as technical counterpoints to the expressive textures and colours of the interior finishes.
TIGHT TIMEFRAME AND MINERGIE-ECO
A major challenge for the delivery team during construction was the extremely tight project timeline. Because of the school term starting in September 2026, the completion date had to be met at all costs. Particular care was required because the basement sits almost entirely within groundwater, and natural groundwater currents could not be obstructed or disrupted.
Special free-draining foundation base layers provide long-term protection, even in the event of short-term groundwater ingress against the structure.
The main electrical utility feed was also unusual. Owing to the school’s high electrical power requirement, it could not be fed directly from the street, but had to be run over an extended distance from the nearest distribution substation located on the northern neighbouring plot. Stringent school building standards regarding acoustic performance, solar shading and indoor climate criteria presented further demanding technical challenges. The building is certified to the Minergie-ECO standard. Its photovoltaic installation provides an estimated self-sufficiency rate of 17 percent. An ecofriendly heat-pump heating system powered by geothermal probes ensures efficient overall energy management.